Daily Construction Reports

Historical daily progress reports by discipline

Reports Submitted
127

100% completion rate

Avg Productivity
102.3%

+2.3% above target

Total Manhours
486K

Project to date

Recent Reports
DateDisciplinePlanned MHActual MHVarianceCrew SizeStatus
TodayCivil850920+8.2%18submitted
YesterdayStructural1,2001,050-12.5%24submitted
2 days agoPiping2,1002,240+6.7%32submitted
3 days agoElectrical780620-20.5%16submitted