Construction Management
Field progress tracking, quality control, and safety management
Overall Progress
58.4%
Manhours Today
5,310
+4.2% vs planned
Active Crews
142
Across 4 areas
Open NCRs
12
3 critical
Safety Days
247
LTI-free
Daily Progress by Discipline
Planned vs actual manhours for today
Civil
920 / 850 MH+8.2%
Structural
1,050 / 1,200 MH-12.5%
Piping
2,240 / 2,100 MH+6.7%
Electrical
620 / 780 MH-20.5%
Instrumentation
480 / 450 MH+6.7%
Site Activity Feed
Recent updates from the field
Concrete pour completed - Foundation F-12
10:45 AM
Safety observation submitted - Area 200
09:30 AM
Morning toolbox talk completed - 142 attendees
08:15 AM
Daily crews mobilized to site
07:00 AM
Progress by Area
Construction progress across project areas
Area 100 - Process
on-trackProgress72%
Area 200 - Utilities
at-riskProgress54%
Area 300 - Electrical
delayedProgress38%
Area 400 - Tank Farm
on-trackProgress65%