Construction Management

Field progress tracking, quality control, and safety management

Overall Progress
58.4%
Manhours Today
5,310

+4.2% vs planned

Active Crews
142

Across 4 areas

Open NCRs
12

3 critical

Safety Days
247

LTI-free

Daily Progress by Discipline
Planned vs actual manhours for today
Civil
920 / 850 MH+8.2%
Structural
1,050 / 1,200 MH-12.5%
Piping
2,240 / 2,100 MH+6.7%
Electrical
620 / 780 MH-20.5%
Instrumentation
480 / 450 MH+6.7%
Site Activity Feed
Recent updates from the field

Concrete pour completed - Foundation F-12

10:45 AM

Safety observation submitted - Area 200

09:30 AM

Morning toolbox talk completed - 142 attendees

08:15 AM

Daily crews mobilized to site

07:00 AM

Progress by Area
Construction progress across project areas
Area 100 - Process
on-track
Progress72%
Area 200 - Utilities
at-risk
Progress54%
Area 300 - Electrical
delayed
Progress38%
Area 400 - Tank Farm
on-track
Progress65%